The 60 MW Bileća solar power plant of the Energy Financing Team (EFT) company, which was built by our company, has been completed.The Bileća solar power plant is located at K.O. Zarečje, which covers 133 hectares. It is two kilometers from the shore of Lake Bileć and one kilometer from the main road Trebinje-Bileć.

The Bileća solar power plant has a maximum installed capacity of 60 MW and an estimated annual production of 84 gigawatt-hours. There are 113,184 panels connected in 4,192 groups mounted on 1,048 trackers.

Electricity from the solar power plant will be sold on the market, and the investment is estimated at more than 53 million euros.

EFT received a concession from the Government of Republika Srpska in 2020 for a period of 50 years, which includes a three-year design and construction period and a 47-year usage period.

The Bileća solar power plant is the first power plant from which the Municipality of Bileća has an inflow of funds.

According to Minister Đokić, Republika Srpska plans to build and commission 1,200 MW of new energy facilities by 2030.

A number of investment projects are underway, with contracts for 1,719 MW of new energy facilities, of which 680 MW will be built by Elektroprivreda Republika Srpska (ERS), and the rest by private investors and partners from Europe and the rest of the world.